A slide from Shannon and Wilson’s presentation showing approximate excavation area.

The busy cruise ship town of Skagway is looking for a solution to the rockslides that continue to pepper its largest cruise ship dock. It also hopes to prevent a major rockslide that experts are calling inevitable. As winter approaches, the window to execute a workable solution gets smaller and smaller. As KHNS’ Mike Swasey reports, a geotechnical engineering firm is working on a project design and made its initial pitch during the last borough assembly meeting.

The Railroad Dock in Skagway has drawn international attention this summer as videos of cruise passengers running from rockslides and clouds of debris have gone viral throughout the cruising community. The forward berth of the town’s largest cruise ship dock was shut down earlier this summer, about a week before a large slide hit the area.

The town has been operating only three out of berths ever since. That’s resulted in the loss of about 125,000 passengers this season. If the community wants to return to hosting four ships at a time in 2023, they’ll have under seven months to fix the problem.

National geotechnical engineering firm Shannon and Wilson made its initial pitch to mitigate the slide potential at the borough assembly’s September 1 meeting. Anchorage-based Geotechnical Engineer, Kyle Brennan’s tone was hopeful but realistic.

“It’s a complicated issue and time is not helping,” said Brennan.

He went on to say that there are approximately 40,000 – 60,000 yards of rock that need to be moved off of the mountainside to prevent both major and minor rockslides. The process will involve mechanically removing the rock, lifting it up over the top of the hillside, and depositing the material out of the way of the view shed of Lower Dewey Lake, then repeating the process down the slope until it is completed.

Another slide from Shannon and Wilson’s presentation showing the disposal area and site access area.

Brennan says there are two problem areas. One is the continued smaller rockslides, of which there have been several over the past few weeks. The other is the large unstable mass at the top of the slope that he says will eventually release and destroy the area below the slide zone, and potentially much more if left untouched.

“What we’re trying to do is twofold. One, remove this very large hazard. But also by doing so we should greatly reduce the amount of rock fall that’s produced along the slope because we no longer have that moving rock mass. The rock fall hazard will never go away completely because you have a steep rock slope and steep rock slopes over time generate rock fall occasionally, but the frequency of those rockfalls should be reduced dramatically,” said Brennan.

The most recent calculations say that the large rock mass is separating from the mountainside at a rate of 2.5 inches per year, up from between 1 and 1.5 inches just a few years ago.

Brennan said his firm will have 10% design plans for mitigation completed by September 16. Without those plans, permits can’t be applied for, grant proposals can’t be made, and a contractor cannot be hired. Even if the 10% design plans are made by the middle of September, it won’t be likely that permits will be approved, even if expedited, until mid-winter. 

“If we can get that contractor on early, you know, there are certain components of the project that maybe they can start that don’t really rely so much on the permitting: staging equipment, establishing access, maybe doing some work to prep the upslope disposal site for the rock.”

That may include improving road access to Lower Dewey Lake to get large excavators and dump trucks to the construction site.

Assemblymember Orion Hanson suggested progress needs to start on those developments immediately.

“Because any suggestion of a helicopter getting a 70,000-(pound) excavator up that mountain seems completely impossible to me,” said Hanson.

And without helicopter-assisted access, road work would need to begin before the winter freeze.

“You’re saying we can’t really do any excavation until sometime in the winter. We have to mobilize well before that if we have any chance of pulling this off before next year,” urged Hanson.

And though the company believes there could come a time when no contractors will agree to take the job because it has become too dangerous, they say that time is not now, and they are confident a mitigation project can work if done expeditiously.

For now, Shannon and Wilson are only focusing on the north slide area above the railroad dock. Project cost estimates and funding options were not discussed in detail.

**This article was corrected from its original airing. Assemblymember Hanson meant to describe a 70,000-pound excavator, not a 70,000-ton excavator.**